Thames Water wastewater upgrade works

We have been advised of upgrades to the wastewater network in Burghclere, which Thames Water will be carrying out from 2 March 2025 onwards. This work will replace 950m of ageing wastewater pipes along Well Street to improve service reliability and prevent future disruptions.

Key Project Highlights:

  • Start Date: 2 March 2025
  • Phase 1 Duration: TBC, subject to site conditions (anticipated to last 3-4 weeks)
  • Future Phases: Residents and businesses will be notified via post as each new phase of work begins.
  • Full Project Completion: Expected by 30 June 2025 (subject to change based on site progress).
  • Traffic Management: Full road closures on Well Street with signposted diversions (Sheepwash Lane remains open during Phase 1).

Further information is available here: Sheepwash Lane SPS-Letter-Of-Notice Feb 25